Projected Costs and Funding Plan

The total cost for the proposed new facility has been estimated at approx. $3.85 million.
Construction$2,500,000
Furnishings$232,000
Technology and equipment$127,000
Professional fees/services (includes moving)$263,000
Contingencies$443,000
Inflation Adjustment (5%)$178,000
Campaign/consultant costs$90,000
Opening day collection (new items for collection)$17,000
Total$3,850,000
Building Fund (cash on hand designated for project)-$500,000
Total Needed$3,350,000
Funding Plan
The first step of the plan calls for raising $300,000 in private support from local individuals, families, businesses, groups and organizations and local and regional foundations.
The second step would be to request a 20 year millage of approximately .6 mills, which would provide funds equal to the balance of the capital project. At present, the library operates on less than one mill of voted support.
The new bond would cost the average home-owner $30 per year for a $100,000 home ($50,000 taxable value).